Selected Projects
Coordination, Arc Flash and Short Circuit Study With a Follow-Up Walk-Down at a Data Center, League City (2017)
We typically respond within one business day.
Project at a glanceDE-PRJ-10885
- Practice
- Electrical power
- Location
- League City, TX
- Service
- Arc flash, coordination, short circuit
- Client
- Confidential
Coordination, Arc Flash and Short Circuit Study With a Follow-Up Walk-Down at a Data Center, League City (2017)
In early 2017 we prepared a coordination, arc flash and short circuit study for a corporate data center in League City, working from field data gathered by the electrical contractor. The study went out on March 13, and the same day we walked the site to check the items it had flagged.
Two ways to power the building
A data center has to keep running on standby power, so the model was run twice: on the utility and on the generators, through the automatic transfer switches. In the normal case 95 buses received a label level, 67 at the lower level and 28 at the next. On generator power the split was 63 and 34. The highest incident energy in both cases was 9.1 cal/cm2, at the primary of one panel. On the utility, the bolted fault current at the main switchboard was about 39.8 kA.
Assumptions and exceptions
Where the field data was incomplete the report says so. The utility transformer impedance was assumed at 5.75 percent, the utility was treated as an infinite bus, and several trip units were assumed from the settings that were reported. One breaker with no model number was left out of the coordination. The report also listed exceptions: at three loads, an air conditioning unit and two elevators, the nameplate full load current equaled the size of the upstream fuse, and seven conductors were flagged for re-evaluation by an engineer.
The walk-down
On March 13 we examined every component referenced in section 4.1 of the report, where the exceptions are listed, and recorded the full load current of the three loads. On March 14 we reviewed the collected nameplates, equipment ratings and wiring. Our memo of March 15 found that no further action was needed and closed the exceptions.
Related services
The study combines our arc flash studies, protection coordination and short circuit analysis, and the follow-up is part of our walkdowns.
Electrical power
Related projects
Pflugerville, TX
Arc Flash Study at a Truss and Wall Panel Plant, Pflugerville
Arc flash, coordination
Greater Houston, TX
Houston Arc Flash Program
Arc flash, coordination
Galveston, TX
Arc Flash Study of a Large Campus in Three Phases, Galveston
Arc flash, coordination
More work in: Texas
Get your project started
We typically respond within one business day.