When we ran our first power station CP survey in Victoria in January 2021, none of its buried piping was cathodically protected. Two years later the newest gas line was fully protected. This is how that happened.

Cable lugs on the output bus of a cathodic protection rectifier at a power station

An old plant and a newer unit

The station has one active gas turbine unit, completed around 2009, beside a decommissioned plant. Soil studies by others put resistivity at pipe depth between 2,000 and 40,000 ohm-cm. The newer unit is fed by a 10-inch fuel gas line coated with fusion bonded epoxy. The original gas piping is out of service, and the original cooling water network, once fed from the river, is still tied in. The 2008 specification for the newer unit called for cathodic protection, and the piping drawings dated from 2007.

What the January 2021 visit found

We walked the plant and tested all eight rectifiers. Seven were 20 years old or more and at the end of their life. One read zero current on its meter; another was found with its main breaker off; a third, for the demineralized water tank, had been switched off by hand. A temporary groundbed test showed which anode beds still had life: those for four of the rectifiers. The 10-inch gas line had no test stations, rectifier or anodes at all, despite the specification, and it was isolated from the supplier by a working flange kit but not at the riser in the plant. The drain and fire water components of the newer unit were not protected either, and none of the buried piping was isolated from plant grounding.

The plan, and the work

We recommended isolating the gas line at the plant end and protecting it with sacrificial anodes, a low maintenance option once it is isolated, doing the same for the buried cooling water piping of the active unit, and replacing the three rectifiers whose groundbeds still had life. The owner asked us to do the work. We replaced the three rectifiers in May 2022, and in May 2023 we isolated the gas line and installed the galvanic anode system.

The 2023 survey

The follow-up survey showed the newer gas line isolated at both ends and fully protected. The old rectifiers were tripping on and off, likely with seasonal changes in soil moisture. On the original piping, most of the protective current still goes to plant grounding and structural steel, and the owner was considering abandoning that piping, so we did not recommend supplemental CP for it. We did recommend inspecting the systems every two months and an annual survey by a corrosion engineer.

Back in 2025

We returned in early 2025 for the annual survey. The newer gas line was still fully protected by its magnesium anode, at -919 mV instant off at the plant riser against a native -538 mV, but the insulating flange kit at that riser had been removed during work on the line and needed to go back in. Of the three rectifiers replaced in 2022, one kept tripping its supply breaker, possibly a faulty breaker, and an older unit had tripped because of a loose, overheated connection in its anode junction box. Four of the eight rectifiers were 20 years old or more and at the end of their life, and only three groundbeds had useful life left. We repeated the advice to check the systems every two months.

Related services

Surveys like this one are described on our page for cathodic protection potential surveys. The new galvanic system followed our approach to cathodic protection design.

Get your project started

We typically respond within one business day.

Request a free quoteor call (866) 621-6920