Evaluation, Redesign and Commissioning of Impressed Current Cathodic Protection for Steel Sheet Pile Wharves, Freeport (2016-2018)

We typically respond within one business day.

Project at a glanceDE-PRJ-8118

Location
Freeport, TX
Service
CP design, testing
Client
Confidential

Evaluation, Redesign and Commissioning of Impressed Current Cathodic Protection for Steel Sheet Pile Wharves, Freeport (2016-2018)

Steel sheet piling in Gulf seawater depends on its cathodic protection, and at the wharves of a port in Freeport that protection had been fading for years. Between 2016 and 2018 we tested the old impressed current system, measured what the wharves needed, and handled the marine CP design and commissioning of the replacement.

Aerial view of a wharf with a ship moored alongside, and a large tank farm and pipe racks onshore.

A ship moored at a wharf. Potentials along sheet piling are read at the surface, at half depth and at full depth, and a docked vessel can disturb the readings.

2016: what was left of the old system

In August 2016 an engineering firm working for the port asked us to check the corrosion control on four of its wharves. The weekly rectifier logs showed 8 of 19 rectifiers switched off for a long time, and a 2014 survey by others had already found five not working. We tested on a Saturday, to stay clear of heavy equipment and large vessels. Seven rectifiers on the older wharves were de-energized, one had been demolished along with its building, and the equipment was in poor repair, with damaged DC conduit and wiring. Injecting current from a portable source gave circuit resistances from about 0.2 ohm to more than 2,800 ohms. One unit had a failed diode stack, and some anode beds looked depleted. Notes on the enclosures from the early 1990s showed rectifiers being run above 100 percent of their rating.

With a silver/silver chloride electrode held in one place, we compared readings at the negative terminals of neighboring rectifiers to test the continuity of the piling. Several sections were not electrically continuous with their neighbors, and two negative leads read like bare copper in salt water, which pointed to failed connections. Only the piling on three rectifiers at the newest wharf was adequately protected. We recommended a full analysis and redesign.

2017: measuring the demand

The port then hired a contractor to replace the 13 rectifiers and deep wells on its older wharves and to confirm continuity along the piling, and the contractor brought us in for the corrosion engineering. Many of the old negative leads had failed and were replaced. In October 2017, near high tide and with the water close to its warmest, we energized an existing deep well from a portable source at 33 V and 40 A and read the piling at intervals out to 610 feet over about two hours. The response worked out to about 2 A per millivolt for every 200 feet of wall. For a 100 mV shift along about 2,900 feet of piling, that meant about 2,900 A, at the low end of published current densities for bare steel in Gulf seawater. The existing system had been sized for less than half of that.

The design, and what was built

We recommended replacing the 13 beds with 200 A deep wells and adding two more, 15 in all, each 300 feet deep with 19 tubular mixed metal oxide anodes, on 75 V and 100 V rectifiers rated 250 A so that storm surges would not trip them. The project specification called for canistered anodes; we advised tubular ones for this high current service. We also checked the negative leads against the NEC® with a temperature derating for Freeport summers. Two existing #2 conductors were enough for 100 A rectifiers, but 200 A would need a third. For budget reasons the port chose 13 new rectifiers and wells rated 160 A, 2,080 A in all, with supplemental protection to follow if testing showed the need.

2018: commissioning

We watched a well being drilled and loaded in March 2018 and came back five more times through September. At first energizing, the rectifiers were delivering 496 A in total. One had abnormal input voltages, and the positive cables to the anode junction boxes were #2 instead of the specified 2/0, so we held the output until both were fixed. In late May we set the rectifiers to about 75 percent of rating, 1,567 A in total, to leave margin for storm surges and seasonal changes. We then ran an interrupted survey every 75 feet along the piling at three depths, with GPS-synchronized interrupters cycling 4 seconds on and 1 second off.

Native potentials had been about -570 to -590 mV against silver/silver chloride; the interrupted readings ran from -580 to -1,100 mV. A discontinuity between two rectifier connections was fixed by welding every joint in that section. Other punch items included negative cables damaged by vessels where a ship bumper was missing, vent pipes that could fill with rain, and two anode junction boxes badly corroded by anode gases. One rectifier, set at 68 percent of its 160 A rating, later showed heat damage on its taps and went back to the manufacturer. An older rectifier left from a failed section of the newest wharf turned out not to be connected to the piling at all.

At the end, about 40 percent of the piling met the 100 mV polarization criterion and the rest had shifted about 60 mV. That is a good start rather than a finished job, so the report called for rectifier checks every two months, a full interrupted survey by May 2019 and every year after that to decide on supplemental protection, and an interference study across the port.

Related services

The evaluation and the redesign followed our approach to cathodic protection design. The 2018 site visits are what we mean by start-up and commissioning.