Soil Corrosivity Study and Cathodic Protection Design for Two Parallel Raw Water Lines at a Regional Water Treatment Plant, North Texas (2019 to 2021)
A regional water district planned two new raw water lines at its treatment plant in North Texas, a 48-inch and a 36-inch line running side by side for about 9,000 feet each. In December 2019 we tested the soil along the route, and our memorandum of January 2020, revised in April 2020, set out how the new pipe should be protected. The cathodic protection design followed.
Twelve test sites, from sand to clay
On December 3, 2019 a crew ran Wenner four-pin tests (ASTM® G57) at twelve locations along the alignment, with pin spacings from 2.5 to 20 feet, and the readings were reduced to layer resistivities with the Barnes method. The ground changed quickly. Sandy sites north of the plant read above 50,000 ohm-cm near the surface, while two sites in an active excavation area averaged roughly 750 to 1,700 ohm-cm. Between 5 and 10 feet deep, the average layer resistivity across all sites was 44,228 ohm-cm, and the lowest was 1,269 ohm-cm.
Five samples from the geotechnical borings went to a laboratory for resistivity, pH and soluble salts. One clay sample read 600 ohm-cm, two samples had a pH of 5.6 and 5.2, and sulfates ranged from about 5 to 499 ppm. The borings also found groundwater as shallow as 4 feet.
What we recommended
Low resistivity and low pH made the clay stretches the aggressive ones, while the sand carried little risk. We recommended sacrificial anodes placed in the low resistivity clay zones, which puts protection where the risk is and also limits interference between the two parallel lines. The memorandum also called for insulating joints with a test station at each point of isolation, bonds across every nonconductive joint, test stations no more than 1,000 feet apart and at cased and foreign line crossings, a dielectric coating made for underground service, wax tape on buried fittings, and dielectric sleeves where pipe passes through concrete. Two gas lines cross the route at right angles, and for the concrete cylinder pipe option we suggested a dielectric wrap for at least 20 feet on each side of those crossings.
The design
The detail sheets cover potential test stations, insulating joint test stations, cased crossing test stations and anode test stations, the anode configuration and alloy, bonding for non-welded and ductile iron joints, wire-to-structure connections and buried taps. The set went through several review rounds in late 2020 and was issued as a conformed set in March 2021.
Related services
The field work is described on our soil corrosivity analysis page, and the design side under cathodic protection design.
Corrosion and CP
Related projects
McKinney, TX
Water Line Soil Study, CP Design and Commissioning, McKinney
Soil corrosivity, CP design, commissioning
Houston, TX
Galvanic CP Designs for Two Water Line Replacements, Houston
Soil corrosivity, CP design
Fort Worth, TX
Soil Corrosivity Study for a 24-Inch Water Line, Fort Worth
Soil corrosivity study
More work in: Texas
Get your project started
We typically respond within one business day.