Licensed Professional Engineers |
Search/

Request a free quote

About

Engineering Support for Electrical Contractors

We typically respond within one business day.

New electrical service switchboard and transformer in an electrical room

When a job needs an engineer

Plenty of electrical work never needs an engineer. Some does: a permit that calls for stamped drawings, a service that has to be shown to have room for new load, an owner’s specification that calls for an arc flash study, or an inspector who will accept an engineer’s report. Dreiym Engineering works with electrical contractors on those pieces, with licensed Professional Engineers and work PE-stamped where required. When you call, you talk with an engineer.

How a job runs with us

Engineering requests on a construction job usually come with a date attached, such as a permit hold, an inspection or a submittal. Getting the right information to the engineer at the start does the most to keep the work moving.

  • Tell us what the job needs. The permit comment, the specification section or the inspector’s request, and the schedule you are working to.
  • Send what you have. Plans, one-lines, panel schedules, photos of nameplates and the utility’s fault current letter if you have one.
  • Scope and proposal. An engineer reviews it and sends a scoped proposal before work begins.
  • Field work where needed. A walkdown, demand recording, a ground test or an inspection, scheduled with your site lead.
  • Deliverables. Drawings, calculations, a study or a report, PE-stamped where required, in a form the plans examiner or inspector can review.

Electrical design

Our electrical design services produce the drawings, specifications and calculations that permitting, bidding and construction need, from a new feeder in an existing plant to a new facility: single-line diagrams, panel schedules, layouts and installation details.

Load studies for existing services

NEC® 220.87 lets the load on an existing service or feeder be set from measured demand. Where a year of maximum demand data is available it is used; where it is not, a continuous 30-day recording of the highest loaded phase, as 15-minute average demand, can take its place. The maximum demand is multiplied by 125 percent and the new load is added to it. Our article on the NEC® 220.87 load study walks through the method. We can record the demand and prepare the calculation, PE-stamped where required.

Have a job that needs a stamp, a study or a test? Request a free quote. We typically respond within one business day.

A 30-day current recording of the highest loaded phase, with a one-day close-up showing motor starting spikes and the peak 15-minute average demand
Only the maximum 15-minute demand from the 30-day recording is used in the NEC® 220.87 calculation.

Arc flash studies and labels

NEC® 110.16 requires equipment likely to be worked on while energized to be field marked with an arc flash warning, and from the 2017 edition, service equipment rated 1,200 A or more needs a label with the nominal voltage, the available fault current, the clearing time of the service overcurrent devices and the date the label was applied, unless an arc flash label to industry practice is applied instead. Our arc flash studies often start from one-lines and walkdown data that the contractor on site supplies, and we print and install the labels, or ship them to you.

Arc flash warning label on the door of a standby generator
An arc flash warning label on the door of a standby generator.

Coordination studies for the AHJ

Some systems must be selectively coordinated, so that a fault is cleared by the protective device nearest to it without opening the devices upstream. The 2023 NEC® requires it for emergency systems (700.32), legally required standby systems (701.32), critical operations power systems (708.54), and elevators where more than one driving machine disconnecting means is supplied by the same source (620.62). The AHJ will want to see the study, with the responsible engineer’s signature and a PE stamp where the AHJ or the owner requires one. Our protective device coordination studies cover this work, and our article on selective coordination explains what the AHJ needs to see.

Grounding, Ufer and pool bonding inspections

We inspect and test Ufer (concrete-encased) grounding connections in new homes and commercial foundations, pool and splash pad bonding, and rough-in wiring, where a jurisdiction accepts or requires an engineer’s report. Our article on alternate methods of compliance explains when an engineer’s inspection can be used in Austin, Dallas and Houston.

How a Ufer ground works, step by step
Drawing of a building footing in soil with a Ufer ground A building stands on a concrete foundation wall and footing set in the soil, with steel rebar near the bottom of the footing. The labels and highlights change with each step, and the caption below the drawing describes each one.
Step 1 of 7What a Ufer ground is
A Ufer ground uses the rebar, or a bare copper conductor, inside a concrete footing in contact with the earth as the building's grounding electrode. The NEC® calls it a concrete-encased electrode. It's named after Herbert G. Ufer, who developed it for U.S. Army facilities in Arizona during World War II, where the dry desert soil made a good ground hard to get.
Step 2 of 7What NEC® 250.52(A)(3) requires
At least 20 ft (6.0 m) of bare, zinc-galvanized or other electrically conductive coated rebar 1/2 in. (13 mm) or larger, or of bare copper no smaller than 4 AWG, with at least 2 in. (50 mm) of concrete around it, in a footing or foundation in direct contact with the earth. The usual steel tie wires may join the bars. Concrete separated from the soil by insulation, a vapor barrier or a film isn't in direct contact.
Step 3 of 7Why it works
Concrete holds moisture, and a footing touches a large area of soil, so a Ufer usually has a lower resistance to earth than a single driven ground rod, especially in dry soil. The drawing compares contact area only. It isn't to scale and shows no measured values.
Step 4 of 7The connection
Where a concrete-encased electrode is present, NEC® 250.50 requires it to be bonded into the grounding electrode system. The grounding electrode conductor (GEC) runs from the service equipment to a rebar stub-up or the copper conductor, connected with a listed clamp or connector, or by exothermic welding. If it's the only connection to the Ufer, NEC® 250.66(B) doesn't require it to be larger than 4 AWG copper.
Step 5 of 7What the electrode does
Connecting the system to earth limits the voltage imposed by lightning, line surges or unintentional contact with higher-voltage lines, and stabilizes the voltage to earth during normal operation (NEC® 250.4(A)(1)). Surge current that reaches the electrode spreads from the footing into the soil.
Step 6 of 7What it doesn't do: clear faults
The current that trips a breaker during a ground fault returns to the source on the equipment grounding conductor (EGC) and, through the main bonding jumper, the neutral. It doesn't go through the earth: NEC® 250.4(A)(5) says the earth isn't an effective ground-fault current path, so even a good Ufer can't do this job.
Step 7 of 7Inspect before the pour, test after
Before the pour, an inspector or engineer checks the bar or wire size and length, the 2 in. of cover, earth contact with no vapor barrier under that part of the footing, and the connection point or stub-up. After the pour, a Ufer can still be tested, for example with a fall-of-potential test.
Need a Ufer ground checked? See our grounding system tests or request a free quote.
Code references are to recent editions of the NEC® (NFPA® 70). The edition your jurisdiction has adopted, with any local amendments, governs. The drawing is simplified and not to scale.

Related projects

What you receive

  • Sealed drawings and specifications for permit and construction, where the job calls for design
  • NEC® 220.87 load calculations, with the recorded demand data behind them
  • Arc flash and coordination study reports, and labels printed and installed or shipped to you
  • Short circuit analysis where equipment ratings or available fault current have to be shown
  • Inspection and test reports with photographs, for Ufer, pool bonding and rough-in inspections

Homes in Austin, Dallas and Houston are covered by our residential inspections; on larger sites, our ground testing checks grounding systems after installation, and our electrical load analysis covers services and feeders beyond a single 220.87 calculation.

Frequently asked questions

When does an electrical job need a PE stamp?

When the permit office, the owner’s specification or the inspector requires one. Typical cases are design drawings for permit, a calculation showing that an existing service can take new load, an arc flash or coordination study, and an inspection where the jurisdiction accepts an engineer’s report.

Can you record demand for an NEC® 220.87 load study?

Yes. Where a year of maximum demand data is not available, NEC® 220.87 allows a continuous 30-day recording of the highest loaded phase, as 15-minute average demand. We can record the demand and prepare the calculation, PE-stamped where required.

Do you print and install arc flash labels?

Yes. Labels from our arc flash studies are printed and installed by our team, or shipped to you to apply.

Can an engineer inspect a Ufer ground before the pour?

Yes, and that is when it has to happen. The electrode has to be inspected before the concrete is poured, and not by the electrician who installed it. Our report documents it for the inspector where the jurisdiction accepts an engineer’s report.

What information do you need for an arc flash study?

One-line diagrams, the utility’s available fault current, nameplate data for transformers and large motors, cable sizes and lengths, and the type, rating and settings of each protective device. Many studies start from one-lines and walkdown data that the contractor on site supplies, and a walkdown fills in the rest.

Talk to an engineer

Have a job that needs a stamp, a study or a test? Request a free quote. We typically respond within one business day.

New electrical service switchboard and transformer in an electrical room

Get your project started

We typically respond within one business day.

Request a free quoteor call (866) 621-6920

Newsletter

Engineering notes from Dreiym

New articles on power systems, corrosion and forensic engineering, by email when we publish. Free account included: keep your calculator work, reports and exports in one place.

One email per new article. Unsubscribe in one click.